06/22 - In Progress
The project, located in Guarulhos, aims to complement/connect the sewage system of the Tietê Centro TC-28 Basin, left bank of the Cabuçu de Cima River – Guarulhos municipal area – with the metropolitan sewage system – Parque Novo Mundo ETE. For this, the scope of the project comprises the Basic Project of trunk collectors, interconnections and isolated interconnections of the basin.
There are plans to install sewage pumping stations, the Parque Continental Repression Line, three trunk collectors (CT Cabuçu ME – Section 1, CT Cabuçu ME – Section 2 and Parque Continental), covering about 5.5 km, in addition to an estimated 8.3km of Isolated Interconnections. Altogether, the project aims to complement a sewage system that serves an area of about 47.5 km².